What settings we need to check in PS module while creating the new plant.

Former Member
0 Kudos

Dear Friends,

If we extending the new plant what all the things that we need to check in Project systems module, what all the configuration that needs to performed. Here we are using the Standard Project structure to creating the projects.

But it is not a manufacturing plant. All the service processes are takes place from this plant.

While creating the plant if we are copying from the existing plant, is that the all assignments are copying to the new plant?

Regards,

Hari

Edited by: Hari Krishna on Jan 5, 2009 10:17 AM

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Hari,

Mainly two settings have to be extended for using networks for that plant..

1) Extending Network type Parameters - T-code - OPUV

2) Production Order control Parameters - T-code - OPU6

Rdgs,

Deepa

Former Member
0 Kudos

hi,

Where ever Plant relavent Settings are coming in Project System which needs to be set.

example : Network type assignment to plant, confirmation paramter for plant. etc.,