Hi experts,

I am not able to view the cost of material component in Structure overview report...but i am able to see the cost of the activity , WBS element...I wanted to see the cost of material component also..pls tell me what is to be done?

Accepted Solutions (0)

Answers (2)

Answers (2)

virendra_pal
Active Contributor
0 Kudos

the cost collector is the activity hence the material cost will be against the activity in str overview report

use CJI3 once the materila is either goods receipted or issued to get cost o material or check CN52N report to see list of components - not sure if there is a procie column but check it out

former_member203108
Active Contributor
0 Kudos

Thanks virendra...I wil chk cji3...i had used cn52n, we can see the unit price by changing the layout...

Former Member
0 Kudos

Hi ,

Go to the network header select Control tab , In selection tab Costing put following parameters,

Costing sheet PP-PC1,Costing varian plan PS02 costing variant act. PS03,Plan cost calc 2.determine plan cost.

save the project and reopen and check for planned cost.System will get material cost from material master.

Rgds