on 01-04-2009 9:29 AM
Hi experts,
I am not able to view the cost of material component in Structure overview report...but i am able to see the cost of the activity , WBS element...I wanted to see the cost of material component also..pls tell me what is to be done?
the cost collector is the activity hence the material cost will be against the activity in str overview report
use CJI3 once the materila is either goods receipted or issued to get cost o material or check CN52N report to see list of components - not sure if there is a procie column but check it out
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
Go to the network header select Control tab , In selection tab Costing put following parameters,
Costing sheet PP-PC1,Costing varian plan PS02 costing variant act. PS03,Plan cost calc 2.determine plan cost.
save the project and reopen and check for planned cost.System will get material cost from material master.
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.