on 01-03-2009 9:42 AM
Hi Gurus,
We have 2 Plant X & Plant Y. During Sales Order processing it is not confirm from which plant the material will be delivered. So we enter Plant X & start the manufacturing in Plant X. Once the material is ready we decide that the material will be delivered from Plant Y . We do Stock Transfer from X to Y.
But as soon as we prepare the Sales Order the Plant field gets grey out as we are using Statergy 85 & project assembly is trigerred during sales order.So it is not possible to change the plant in sales order.
Is there anyway to change the Plant during creation of delivery.
Also when we do the Availablity Check in VA02 system doen not display the Other Plant option in Availablity Control window. We are using Req Type Class 212 & Req Type KMPN.
Thanks in advance.
Regards,
Mahendra
Hi Bala
According to my knowledge you cant change the plant in delivery or in delivery creation because delivering plant is an important parameter for shipping pt determination along with loading group and shipping conditions and since a delivery is always initiated from a single shipping pt and shipping pt is already determined you dont have any chance
It has to be done in Sales order itself that is in VA02
select the item--item details-shipping tab there you have to change the plant and redo availability check and save
I feel the plant will be editable mode there as long as you have not created the delivery in VA02
According to your statement that at order stage plant X is put in sales order and the manufacturing process starts in plant X
That means it is MTO scenario
You can change the plant in VA02
Regards
Raja
Pls avoid posting the same qn in multiple forums
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.