Dear all,

Why constraints comes as must start for activity as i plan date for internal process activity?

I need to plane start and finish date for activities .As i put basic start and fining date in dates

tab page constraints (must start on,must finish on) comes automatically and if i want to

schedule it prohabit scheduling.

What are the problems?

Need help.

Sukhveer.

Accepted Solutions (0)

Answers (1)

Answers (1)

venkatesh_kulkarni1
Active Participant
0 Kudos

hi,

it completely depend on scheduling statergy,

like Free, Bottem up...... and WBS Determining Date or Network Determine dates.....

for activity you need to give the duration in days and just maintain relationship between activities,

then you shcedule your project.

if you give dates for activity then that will be the constrain for that activity, it will not take part in scheduling....as you entered dates manually......

Venkatesh

sukhveer_singh2
Participant
0 Kudos

Thanks for ur valuble help.

Point is clear.

Rewards points for ur valuable help.