Dear Gurus
I have budgeted WBS in 2008 for USD 2000. My controlling area currency is INR
In 2008 USD to INR conversion rate for M is maintained as 42.
When I executed standard budget/actual/commitment report in 2008 report displayed as INR 84,000 then I selected currency transation and selected currency as USD and transalation key as 1 (mean rate today).
In 2009 I have maintained conversion rate for USD to INR as 44 for M.
and in 2009 when i executed standard budget/actual/commitment report diplaying in INR correctly as 84,000 but in USD it is displayed as $ 1909 (84000/44) with currency transalation key 1.
I tried to select currecny translation key as 5. But system not allowing me select that key.
But I want to see the original budgeted amount in report.
Kindly some help in this regard.
Thanks
RK
hi,
Original Budget can be seen in CJ31 Transcation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.