Delivery date in the purchase order

Former Member
0 Kudos

Hi all,

Iam creating the standard P.O. today 2nd Jan.System is taking the delivery date as 5 th Jan ie..after three days.

How system is calculating this?

I know this is MM related But is is quite confusing when I practise Schedluing & avai check

Regards

Mano

Accepted Solutions (0)

Answers (7)

Answers (7)

Former Member
0 Kudos

xvxc

former_member192897
Active Contributor
0 Kudos

It will Pick from Purchase Info Record Planned Delivery Time.

Former Member
0 Kudos

Hi,

Check factory calender. E.g Factory calender - US

Goto SCAL t.code. Select factory calender field. choose change / display icon.

Select the calender and click on definition. Here you will get working days.

Goto vendor master data, Enter vendor number,company code and purchase org.

Check planned delivery time in purchase data screen.

Regards,

Chandra

Former Member
0 Kudos

Hi Mano,

1st of all, you need to check whether there is any purchase infor record which is maintain for the particular material and vendor using tcode ME13, inside purchase organization data 1, if you got maintain plan delivery time, then system will take that into consideration.

Else, you can check on MRP2 in material master view, if you got maintain planned delivery time, then system will take this into consideration if you dont maintain the plan delivery time in purchase infor record.

Hope it is clarify for you.

Former Member
0 Kudos

Check in the Vendor Info record for that material in TCode ME12. The Planned delivery time could be given as 3 days.

Former Member
0 Kudos

Hi,

you don't want to get that message in PO.

Goto IMG>MM>Purchasing>Environment Data>Define Attributes of System Messages>System messages.

Remove the category W- warning.

Version 00-

Application ME

message number 40

Regards,

Chandra

Former Member
0 Kudos

Hi,

Check the factory calender. As it might have this days listed as holidays.

Regards

AK