In which tables (ABAP) the Project System Information Will be stored

Former Member
0 Kudos

Dear Guruu2019s

Happy New Year

In project systems can we able to see, against the projects and against WBS what all the sales orders, Employees and material etc... That we assigned, in which STD report we can check all these assignments, from which tables (ABAP) it picks up the data to populate in the STD report.

I need the Tables for preparing the Z- Report. Please help meu2026

Regards,

Bhanu Prathap

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Try report CNS41, use DB profile to fullest extent (Tick relevent data). It gives you the sales orders, materials, person resp. in the project.

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks for the reply's

Former Member
0 Kudos

The most common overviews with respect to sales and distribution can be obtained from CN54N/ CN55N or you can also use CNS54 / CNS55. Tables for the same are VBAK/ VBAP.

For materials you can refer to CN52N overviews for material components and CO24 for missing parts.

For resources, CN50N provides the capacity requirements and CMP9 workforce planning.

Venu