on 12-31-2008 8:45 AM
Hello Guru's,
Initially I wish u all a very very happy new Year 2009.
I have one problem regarding the grouping WBS element,
I have initialised the grouping ind. in the Project,so all the WBS element's related to this project will consider all the stocks when MRP runs.
So, I have procured some parts against one WBS elements via PR/PO.
The other WBS element's have these parts in finish code BOM along with others.
When i carry the MRP for this WBS , The whole BOM materials r not planned instead it is considering only the parts procured from first WBS only.i.e. BOM is not exploding.
Is there any other settings to be check?
Thanks in advance.
Subhash
bom date problem
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
prerequisites for requirements grouping
Project definition
should be valuated project stock
should have automatic requirements groupings ticked
WBS element
Select one WBS usually top level as grouping WBS
PS customising
MRP group that allows grouping
Material master data
Planning screen 1 - MRP group that allows grouping
Material must be managed using sales order stock or project stock
Materila Lot size cannot be "exact", should be periodic
check all these and you should be OK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.