Hi experts,
can anybody explain me what is Backflushing and when we should use this tick ?
Thanks
Ashis
Hi Ashis,
Each material component is assigned to an operation in the production order. If a material component is backflushed, the system posts the withdrawal only upon confirmation of the operation. The withdrawal is then posted automatically {Backflushing is automatic accounting (Goods issues - 261 mvt) of material consumed for production, at the time of confirmation.}.
Backflush is used for material which are a must and having fixed relationship.
This can be configured in MRP2 Screen, Work centre, Routing or production order.
Also refer the below links :
http://help.sap.com/erp2005_ehp_04/helpdata/EN/92/91a812a9d511d189090000e8323492/frameset.htm
With Regards,
Pragna
Edited by: Pragna Korat on Dec 31, 2008 7:34 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.