Hi!

How to make Work Center and Plant Field mandatory in CJ20N transaction?

Bekele

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

Try this..goto OPUC and select those fields as required

Answers (2)

Answers (2)

MohanDesai
Active Participant
0 Kudos

Thanks

nitin_patoliya
Active Contributor
0 Kudos

If we write more correctly than

if you wanted to have required field in WBS than use txn OPUK

if you wanted to have required field in Network header than use txn OPUA

if you wanted to have required field in Network activity than use txn OPUC.

Regards

Nitin

nitin_patoliya
Active Contributor
0 Kudos

You can do the same in OPUK txn for the plant. if you make mandatory for all the projects than tick the required radio button for plant.

By using infuencing filed you can make mandatory plant at project profile level also. say if the project profile is x0001 plant will become mandatory.

I am editing the thread for the workcenter you can achieve the same by using OPUC as suggested by Ahmed.

Regards

Nitin