Hi experts,

I hav planned for 50components in project and the reservation was created...goods were issued against the reservation..now I need 10pcs of the component more...Is it possible to issue these unplanned material to project without reservation..if so how it is to be done...

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

do MIGO - goods issue

choose order and enter network and activity

former_member203108
Active Contributor
0 Kudos

Hi virendra..i tried that..it shows only the other balance material components reserved for the network and i m not able to add the required material in that screen...even i tried unchecking the final issue box for that particular material overview screen in project builder. but still useless....any other solution..

(PS. I am not maintaining any project stock and the materials are reserved for network)

virendra_pal
Active Contributor
0 Kudos

in the middle of the MIGO screen there is an insert button (has a green plus sign) use that to change the quantity or add new material

former_member203108
Active Contributor
0 Kudos

Thanks virendra...problem solved