I have small clarification, if we have 10 plants and two materials, how many master records we can create.

Regards

T.Srikanth

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

If you see the table MARC you need to create 20 record if u wnat to extent both the material in 10 plants.

Thx.

Edited by: Dwarkesh Thakkar on Dec 30, 2008 6:04 AM

Answers (5)

Answers (5)

Former Member
0 Kudos

Dear Srikanth,

If, you are gonna use both the Materials (say, 001 and 002) in all 10-Plants; You need to create Both the Materials with 1 Plant, respectively, and extend both Materials in rest of the Plants.

Best Regards,

Amit

Note: Also, maintain necessary assignment in to -

T. Code: OX18 - Assignment: Plants-> Company Code

T. Code: OVX6 - Assignment: Plant-> Sales Org/ Dist. Chnl

T. Code: OVXC - Assignment: Shipping Points-> Plants

Former Member
0 Kudos

First create material material for one plant and then extend this to other plants.

then only you can enter manual plant in sales order.

Regards,

Abhee.

Former Member
0 Kudos

HI

create 2 material master records and extend the same materials to all the plants

regards

former_member204513
Active Contributor
0 Kudos

Dear Srikanth,

Single Master data is enough for each material.

You can create single master data under one plant later you can extend the same master data to other 9 plants through MM01 transaction.

I hope this will help you,

Regards,

Murali.

Lakshmipathi
Active Contributor
0 Kudos

Dear Srikanth

Just creation of two material codes is enough. While sale order creation, maintain the delivering plant there.

thanks