cancel
Showing results for 
Search instead for 
Did you mean: 

Scheduling Agreement- ANY IDEAS FROM GURUS?

reazuddin_md
Active Contributor
0 Kudos

Hai ALL,

I have a req-

Customer will place order with pre-defined schedule for the next month ( including schedule dates & Qtty).

When User creating Sch.Agreement-VA31,

Enters Material in line item & Total Qtty ( total req for the next month), then this qtty has to be divided equally into next month working days(will get from Factory Calender) into schedule lines.

Is there any BDC, so that whenever user enter material & qtty, schedule lines can be divided into day wise in schedule lines tab?

I have tried this from std, but i couldnt find.So thought of use BDC to split monthly req into day wise.

Any Thoughts

Edited by: SAP Consultant- on Dec 30, 2008 10:52 AM

Accepted Solutions (0)

Answers (2)

Answers (2)

reazuddin_md
Active Contributor
0 Kudos

RAISED SAP NOTE,

Former Member
0 Kudos

I hope the function you are working is a part of standard functionality.

Have you assigned the spilting rule correctly:

T-code : Vozp

Depending upon the rule ,system creates the ratio to divide the quantity over the period of time specified.

What rule have you specified and calculated?

regards,

A S

reazuddin_md
Active Contributor
0 Kudos

THanks for your reply,

I have created my own rule by copying from SAP1.

assigned this rule to instructions.

created sch.agreement with Doc type:BL/LZ

assigned instructions in control parameter tab.

still sch.lines not splitting.

can you explain, how splitting works while doing transaction?

Have read SAP Help & customized according to that, But it is not splitting, checked SAP Notes, but nothing solves my problem