My question is
1. I have structured a project
2. Defined dates for project and WBS
3 Defined activities and duration
3. Defined relationships
4. went to planning board and then opted for bottom up scenario and scheduled it ....................
the planned dates are going into the past .............................??????
i have planned dates of WBS(root WBS) , starting from today to 45 days ...........and even planned the dates for the 2nd level WBS , starting from today ..........................
Any mistake in the procedure??
pls guide me ............
wht r the checks i can do?????
thanks a lot guys
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
My question is
1. I have structured a project
2. Defined dates for project and WBS
do not do this at this stage
3 Defined activities and duration
3. Defined relationships
4. went to planning board and then opted for bottom up scenario and scheduled it ....................
use free scheduling instead of bottom up
now when you schedule the dates from the network activities will go to the WBS to whihc the activites are assigned
then in planning board
Edit-> reconcile dates -> extrapolate
this will update the higher level WBs elements
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Surya,
Please follow the links mentioned below, here you will find everything related to scheduling :
http://help.sap.com/saphelp_45b/helpdata/en/c0/1885347860ea35e10000009b38f83b/frameset.htm
http://help.sap.com/saphelp_46c/helpdata/en/3d/72369adc56d11195100060b03c6b76/frameset.htm
Thanks,
Dhruv Kumar Malhotra
Edited by: Dhruv Kumar Malhotra on Dec 30, 2008 7:19 AM
are you sure you are doing free scheduling
also check the dates in past field
in planning board click on the options button and check the parameters
scheduling scenaio - free scheduling
for WBS - plan basic and forecast - open planning
WBS scheduling profile - forward
scheduling type - forward
sch method - network determine dates
no reduction
start in past = blank
make sure that all the dates in the project definiton and WBS are balnked out
yes, i have already check it and changed it and the problem is solved right now
tell me one thing, this "START IN PAST" is only for scheduliung ........??
i have cleared it and is working fine ........................does it has any impact anywhere else?????
for partially confirmed activities .........................are the following steps are good?
1. Partially confirmed activities.
2. free scheduling with shift order ...............scheduled it
3. now can i go for bottom up? ?????? any impact ???????? if i do schweduling with the following parameters??????????
pls confirm me whether i am going in right direction?
now that your basics is cleared
yes you can try bottom up now
set shift order as you want for partially confirmed activities
there should be no impact
but as a general rule ytou should usually follow only set of scheduling rules
for trial and error you can do whatever
start in the past is ot usually used as most project managers prefer today scheduling
i.e. what happens from now on
Edited by: Virendra Pal on Dec 30, 2008 10:49 AM