Dear Guru's,
We are assigning Employeeu2019s in u201CActivityu201D u201CPersonal assignment Tabu201D, for these employees we are booking the u201CTime sheetu201D against u201CNetwork activityu201D.
Are there is any standard report is available to view the Employees those are assigned to the Project. If it is available please provide the Transaction Code.
Regards,
Bhanu Prathap
you should assign employees via work forcxe planning transaction CMP2
use txn CMP9 for evaluation
if you use the tab as suggested you should be able to get details from CN47N
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Nitin is correct if there is no HR then it is difficult to set up resource planning based on workforce. Nitin is also correct in poinitng out that yu do not have to implement HR fully, just set up the personeel master data (HR Mini Master) with a basic set of data infotypes.
If however you do not plan to set up HR ot the personnel master then you need to do creative thinking - e.g. set up all your people as individual work centres and assign to activites - the work centre description can be the name of the person and the workcentre number can be the employee number - restrcitcions is the field length, etc - however the down side of all this is that standard reports with personnel number number will not suffice and you will have to do some work for your reporting - not major as the data is stored in SAP tables