Std report T.Code to view the Employees those are assigned to the Project

Former Member
0 Kudos

Dear Guru's,

We are assigning Employeeu2019s in u201CActivityu201D u201CPersonal assignment Tabu201D, for these employees we are booking the u201CTime sheetu201D against u201CNetwork activityu201D.

Are there is any standard report is available to view the Employees those are assigned to the Project. If it is available please provide the Transaction Code.

Regards,

Bhanu Prathap

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

you should assign employees via work forcxe planning transaction CMP2

use txn CMP9 for evaluation

if you use the tab as suggested you should be able to get details from CN47N

nitin_patoliya
Active Contributor
0 Kudos

In Addtion to it, As you have assgined employees to activity personnnel assignment tab, you can use CN48N - Confirmations for the reporting purpose.

Regards

Nitin

Makal
Active Contributor
0 Kudos

Virendra

please correct me, if i'm off track.

Workforce planning can be done, if HR module is implemented right?

Take for example there is no HR module implemented/ don't have plan to implement it.

In this case, how do you do work force planning?

nitin_patoliya
Active Contributor
0 Kudos

Prerequisite for the Worforce planning is that SAP PS is provided with Various HR master data.

The minimum requirement is that HR Master data of the InfoTypes 0001 ( Organisation assignment ) & 0002 ( Personal Data ).

Also refer this post.

Regards

Nitin

Makal
Active Contributor
0 Kudos

Thanks for reply Nitin.

In case there is no HR module. Then how do you plan resources?

nitin_patoliya
Active Contributor
0 Kudos

Amresh,

If HR module is not there than it seems that not possible to make resource planning, Let us wait for Virendra / other's view on it.

Regards

Nitin

virendra_pal
Active Contributor
0 Kudos

Hi

Nitin is correct if there is no HR then it is difficult to set up resource planning based on workforce. Nitin is also correct in poinitng out that yu do not have to implement HR fully, just set up the personeel master data (HR Mini Master) with a basic set of data infotypes.

If however you do not plan to set up HR ot the personnel master then you need to do creative thinking - e.g. set up all your people as individual work centres and assign to activites - the work centre description can be the name of the person and the workcentre number can be the employee number - restrcitcions is the field length, etc - however the down side of all this is that standard reports with personnel number number will not suffice and you will have to do some work for your reporting - not major as the data is stored in SAP tables

Answers (0)