Hi Experts,
In our Scenario,the PRs for the Service and material are generated during release of the WBS element or activity.
But we r planning to restrict some PR generation after release using User status.So for materials there is business process "Material Purchase requisition " which can be forbidden,but i dont know which business process is to be forbidden for service PRs.Plz suggest....
Thanks in advance
Dear All
Already i checkeed the business transaction in user status, but i didnt find where the "no P/R is not required". Please guide me where the field is?
thanqu
raj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
The Business transaction "Material PR creation" doesnot have effect on Service PR.
Best possible thing to do might be -
1. Set the Res / PR indicator to "From Release" & make it greyed out (may be using Screen variant)
2. Forbid "Release" of activity using a user status as long as required.
regards
it should be the same - try with that
alternatively you can also set the indicator Never for preq creation
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.