Hi,
Is there any settings in SPRO for assigning standard milestones to Standard WBS/Activities.
One more query is that can we see list of projects what we have done for the client.
Thanks in advance,
Regards,
Suresh.D
1. Is there any settings in SPRO for assigning standard milestones to Standard WBS/Activities.
You can assign a std. milestone to std. WBs / Activity.
this can be achievey via any maintenance txn of std structure network / WBS.
say for ex. CJ92 --> enter your std. PD. --> F5 ( go to std. WBS element overview ) -->select the std. WBs for which you want to assign the std milestone --> WBS element ( milestone overview) --> click on 'inst. std. milestone' button (F5) --> sys will give you popup window for the selction of std. milestone --> select it -->save.
2. To see list of projects what we have done for the client
In all PS reporting txn you can achieve this better to use CN41 --> give ( * ) in the project filed and execute without any restriction.
But more convienent way to do this type of analysis is use of SE16 --> give table name say for the project give "PROJ' > F7> remove the restiriction of max. no. of hits.--> F8.
(In txn SE16 by using setting menu--> Field for selction / Choose Field you populate the data related to your analysis instead of whole table data and export the same to Excle file )
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.