Possibility of assigning standard milestine to standard WBS and Network

Former Member
0 Kudos

Hi,

Is there any settings in SPRO for assigning standard milestones to Standard WBS/Activities.

One more query is that can we see list of projects what we have done for the client.

Thanks in advance,

Regards,

Suresh.D

Accepted Solutions (1)

Accepted Solutions (1)

nitin_patoliya
Active Contributor
0 Kudos

1. Is there any settings in SPRO for assigning standard milestones to Standard WBS/Activities.

You can assign a std. milestone to std. WBs / Activity.

this can be achievey via any maintenance txn of std structure network / WBS.

say for ex. CJ92 --> enter your std. PD. --> F5 ( go to std. WBS element overview ) -->select the std. WBs for which you want to assign the std milestone --> WBS element ( milestone overview) --> click on 'inst. std. milestone' button (F5) --> sys will give you popup window for the selction of std. milestone --> select it -->save.

2. To see list of projects what we have done for the client

In all PS reporting txn you can achieve this better to use CN41 --> give ( * ) in the project filed and execute without any restriction.

But more convienent way to do this type of analysis is use of SE16 --> give table name say for the project give "PROJ' > F7> remove the restiriction of max. no. of hits.--> F8.

(In txn SE16 by using setting menu--> Field for selction / Choose Field you populate the data related to your analysis instead of whole table data and export the same to Excle file )

Regards

Nitin

Former Member
0 Kudos

It solved the problem.

Thank you,

Suresh.D.