on 12-29-2008 7:23 AM
Dear Guru's,
What is Project Version? What is the Use of it? How to do this?
Regards,
Kalyan
Please refer this online help.
http://help.sap.com/erp2005_ehp_04/helpdata/EN/d8/1fe8344d1d166be10000009b38f83b/frameset.htm
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
project version is a snapshot of the project at a given point in time.
It is mostly used for evaluating milestones using the milestone trend analysis to establish if your project is on track or not
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Project Version is like a snapshot of the project status at any point of time. Any number of project versions can be created.
Using these one can compare the project changes at different points of time.
Use CN72/ CN71 to create project versions as per requirement.
Venu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.