How to do Goods issue for quality inspection stock

Former Member

Hi gurus,

we are having one scenario,In that we need to post Goods issue for both unrestr and QI stock,we created stock transport order and delivery using that QI stock also,But we are not able to do PGI....Is there any config for this?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

You cannot do PGI using stock lying in QI stock. You have to move to unrestricted S.loc and do PGI.

Regards,

R.Janakiraman

Former Member
0 Kudos

hi ,

As per our sceanrio we need to do PGI for intercompany stock transfer only(replenishment)..we are maintaining QI stock for that material only.

former_member217082
Active Contributor
0 Kudos

Hi Nagarithanam

As your material is a QM material at the time of PGI it is getting blocked. But as you want to do PGI for Unrestricted and QI stock then first of all go to MM02->Quality Inspection tab-> in this tab click on the inspection types check wheather which inspection has been assigned 02 or 10 ( Cust order with delivery to do PGI ) delete that inspection type and save the MMR and then you can do PGI (without blocking the PGI quality inspection)

Regards

Srinath

Former Member
0 Kudos

Hi guru,

In our material master there is already no value for inspection type.but still we are not able to do PGI.we want to post QI stock also that is our requirement.