Dear Guru's,

Where can we check the Project closing status? Can we change the closing status if want to do some modification, and what is the transaction code that we to view the list of closing project.

Regards,

Kalyan

Accepted Solutions (1)

Accepted Solutions (1)

nitin_patoliya
Active Contributor
0 Kudos

1.You can find the project status ( all the status ) in any project maintenance transaction for ex. Run Cj20n > Open you project> on the basic data tab you will find the project status.

( If you want to see the status of other PS oject than click on that object, similarly you will get the status of that object on Basic data tab. )

2.Yes you can change the closing status of proejct for midification. path is clickon the object for which you want to change the closed object > Edit> Status--> Close --> Undo.

3.For the list of Project status go to CN41

on the projectno. input line click on multiple selection--> give the proejct no. list for which you wanted to see the status. -->enter --> Excute.

Report will open in screen. in that report go to toolbar and click on 'choose filed' button.(F5) -->one pop up window will open -->right handside scroll down in that window >select 'status' field and move it to left side>enter

project status will be shown against you project list. you can verify the same in maintenance txn.

If you have activated user status the same will also get populated.

You can downlaod the same in Excle file path is : Evaluation menu>export>save to file. ( via filtering in Excle you call do all the analysis realted to project status how amny are in clised status etc. )

Regards

Nitin

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

You can get the list of closed projects from table JEST. Put I0046 in the field "STAT" ie.status and then search for the objects. (put PR* in the object field to keep the search specific for WBS).You can revert "close" status of the project.