Hi,

I have maintained the quality procurement key active in the material master.

I have assigned the CONTROL KEY to lock the MIRO before clearing the inspection lot.

But its still allowing to do MIRO.

I have checked the SPRO every thing is maintained correcty.

Plese any one can tell me the solution.

Regards

Shru

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member187991
Active Contributor
0 Kudos

hi

check the control key in IMG settings whether Block invoice is activated

regards

thyagarajan

Former Member
0 Kudos

Hi

thanq for ur reply.

In IMG every thing is maintained correctly.

Regards,

Shru

Former Member
0 Kudos

Hi,

If you want to restrict MIRO, Select control key u201C0007 - Del. released,Invoice blocku201D in QM view of material master.Ensure the below mentioned spro settings.

Path: SPRO> Quality management> QM in logistics-->QM in Procurement -->Define control keys.

Select control key u201C0007-Del. release, invoice blocku201D in change mode, select indicators u201CRelease requiredu201D, u201CBlock invoiceu201D and select the message mode as u201C E defectsu201D.

If you only want to pay invoices, when the quality management process has accepted goods or waived a goods receipt inspection, you must ensure that invoices are not entered before goods receipt.

Check it and revert back

Regards