Hi SAP Experts,
When I am running the report s_alr_87013531 the actual expenditure is zero.please tell me from where it capture the relevent data.Whatever I am procuring for an activity Its cost is coming under actual cost and plan cost is coming form material master.Even direct payments against wbs and expenditure through f-02 are coming in actual cost.I want to know what will come under expenditure column and where i will have to maintain the values.
Regards,
Brijesh.
Hi Prabhu
The T Code S_ALR_87013531 is more relevant to look for Revenue based.
You would be able to view the following reports by click on icon "Call up report"
Project actual cost line items
Project plan cost line items
Project commitment line items
Project budget line items
Project structure plan costs line items
Project actual payment line items
Project plan payment line items
Project results analysis line items
Besides above, you can get actual and planned costs report in S_ALR_87013544.
coming to back capturing relevant of actual cost data, that's all depending the selction of various cost elements while posting. you can check with your CO consultant for CE structure and find out whether postings are taking proper place.
Hope this will suffice your requirements.
Regards,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.