Hi,

There are two PPMs for a sku and both are active/valid. My problem is that I am not able to key-in planned order in PPT as these fields are greyed out.

Any inputs ar welcome

Thanks

Vard

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello ,

Kindly check the factory calender in the resource of ppm. Check the working days available for the resource. It could be one of the reason why the fields are greyed out.

Thanks& Regards

Abhijit S Nakhwa

Former Member
0 Kudos

Thanks for the input.

I am getting a message- timstream from resource not valid for total display period.

Any clue why it is coming? is it the same problem?

Former Member
0 Kudos

Hello ,

Kindly check the settings for following.

1. In the resource , in the 'General Data ' check the validity period of the available capacity of resource

specified in number of days.

2. Also check the 'production calendar ' assigned to the location,in which you have defined the resource..

The time stream of the production calender may have to be extended.

Thanks & Regards

Abhijit S Nakhwa

Edited by: Abhijit Nakhwa on Dec 31, 2008 11:08 AM

Former Member
0 Kudos

Abhijith,

I checked both and are in place. I thing this is related to resource. But not sure how to tackle.

Vard