initiating project version creation automatically

Former Member
0 Kudos

hi all

Pls guide me how we can create project version automatically

regards

KP..

Accepted Solutions (1)

Accepted Solutions (1)

nitin_patoliya
Active Contributor
0 Kudos

Project versions are:Time-dependent Status-dependent

Time-Dependent

At a particular point in time, you create a project version manually. You can do this in the WBS, network, or information system.

Status-Dependent

The system automatically creates a project version when there is a system and/or user status change in the selected objects. You define the user/system statuses which trigger creation of project versions in Project System customizing.

you have to do customisation setting related to Project version profile in customisin. path is SPRO> PS>Project version ( OPST) txn.

For details please refer

http://help.sap.com/erp2005_ehp_04/helpdata/EN/ee/41f17a46ee11d189470000e829fbbd/frameset.htm

Regards

Nitin