Pls guide me how we can create project version automatically
regards
KP..
Project versions are:Time-dependent Status-dependent
Time-Dependent
At a particular point in time, you create a project version manually. You can do this in the WBS, network, or information system.
Status-Dependent
The system automatically creates a project version when there is a system and/or user status change in the selected objects. You define the user/system statuses which trigger creation of project versions in Project System customizing.
you have to do customisation setting related to Project version profile in customisin. path is SPRO> PS>Project version ( OPST) txn.
For details please refer
http://help.sap.com/erp2005_ehp_04/helpdata/EN/ee/41f17a46ee11d189470000e829fbbd/frameset.htm
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.