We want to create snp planned orders with non pegging relevant by using snp optimizer, how can we do this?
Regards,
Burak
Hi Burak,
In IMG, use the following menu path
SAP SCM Impl Guide --- APO --- Supply Chain planning --- PPDS --- Global settings --- Maintain Global parameters and values --- Under Planning Tab --- Activate fixed pegging.
This is universal setting for the entire client.
Hope this helps.
Please confirm
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Burak,
During planning run, include the items for which non-pegging is required and then carry out the run. Once the run is complete, carry out another planning run with pegging relevant items by changing the pegging indicator in the customisation field.
Hope this will help to solve your query.
Please confirm.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Burak,
In the Global settings in customisation, set the pegging indicator as inactive.
Hope this helps your query. Please confirm,
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.