Dear All,
i am creating sales order of past date. Enter req. delivery date past,pricing date past. But system is confirming schdule line on today's date. Hence it is not allowing me to create delivery in past.
Aval. check is '02,.
Any I/P on this issue.
Best Regards
Sainath
Dear Sainath
Try with this method.
In VL01N, maintain the "Selection Date" as it is (by default, system date will flow) and change the "Actual GI Date" and do PGI. Of course you may be aware, you can predate to previous period only if the MM period is open; otherwise, you have to post in current period only.
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
what you have written is write. I have already done this.
But i want to know why system is giving today's date as schedule line date.
Even I trying to change manually,system giving warning and changind today's date.
I think it should allow to schdule on past date also.
Do you want to say anything about this?
Regards,
Sainath
Dear Sainath,
First Check:
T. Code: VOV8
Select your Salese Doc. Type and go in to Details-Page.
Uncheck Box: Proposed Delivery Date
As, it will always Delivery Date as Today's Date in Sales Order
Best Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Even stock is available on past date.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.