Hi experts

I would like to distribute the quantity mentioned in my internal activity. I have tried that SAP020 in "Diskeycapreqlt".

when i run cn48n it is not showing the distributed quantity.

pl let me know how to distribute the quantity day wise/month wise and where i can see the result as planned value for the concerned period.

Thanks & regards

pavan

Accepted Solutions (0)

Answers (1)

Answers (1)

Makal
Active Contributor
0 Kudos

Please elaborate more about your requirement. That would help to understand your issue & answer.

0 Kudos

Dear amresh

I have given my Internal activity Qty is 1000 M3, but i want it to be distributed over project. Say monthly distribution. Means my planned quantity will be 300 m3 for december,200 m3 for january etc. like that.

I want to see the report for a particular month say december, my planned qty is 300m3 and actual is

270m3, rather than 1000 m3 is my planned, i would like to see 300m3.

In CN48n remaining work should be 30m3 rather than 730m3.

I'm trying with distribution key concept. but no result yet.

hope you got the clarity now.

pl help me

regards