Overall budget less than overall release with CJ35

Former Member
0 Kudos

Hi

When I retrun amount from Project through CJ35 system gives me following error:

"Overall budget less than overall release"

Any other steps requires before Returning Budget?

Regards

Sujit

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

I sense that the overall budget is distributed over a time frame of more than 1 year.

Part of the budget was released for the current year... and some of it was consumed.

Now you wish to return the surplus.

2 cases here.

Return in the project (not the cause of error msg that you are getting) and

Return from the project.

Here in second case when you do the CJ52 Transaction on the distributable budget, the system updates the returns within the project, meaning that the total budget is reduced accordingly.

Kindly refer this link below. Hope this info helps

http://help.sap.com/saphelp_erp60/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm

Regards,

Pradyumna

Former Member
0 Kudos

Hi! Pradyumna

Thanks for reply...

But kindly let me know you are taking about CJ32?

You have mentioned CJ52?

Regards

Sujit

Former Member
0 Kudos

Typing mistake,

CJ32 : Change Release budget

Edited by: Pradyumna Kulkarni on Jan 1, 2009 11:15 AM

Former Member
0 Kudos

reduce the released budget by the amount you want to return. then carry out return transaction

regards

prashant