Good Day All;

The following is the process we use to create Issues and Change Requests.

Team Leader in SOLAR01

Creates the Issue against a Business Process

Creates Change Request

Assigns a Team member to the Change request.

Team member in CRMD_ORDER

Adds all documentation and informs Team leader the change request is complete.

Change request is sent to Release Management for approval.

I can not seem to find a way to relate the change request to the Business Process.

Why is this needed? If SOLAR02 to the u201CConfigu201D, how do they know what Business Process to use?

Thanks All

Regards

Don Newton

Accepted Solutions (1)

Accepted Solutions (1)

raguraman_c
Active Contributor
0 Kudos

Hi,

Please check the TCODE SOLAR_EVAL. You can give project details under project header.

This should help you.

Feel free to revert back.

--Ragu