on 12-22-2008 11:11 AM
Hi all
Planned goods issue date appearing in VL03N is a holiday in factory caldender.
please let me know the reasons . The factory calender maintained in plant and shipping point are correct.
Please let me know the reasons
Regards
Anil
Dear Anil Mairpady
the Planned Goods Issue Dates Takes into considrations the lead time for Production if internally or the Lead time for the Procurement.
Depending on the ATP logic and your material master Setting.
The Date is determined automatically.
If you want to change the planned GI date then you have to configure the MMR is such way or The Stocks has to be present in the same date of the Delivery creation.
Now What We can Help you is if you want to change the Factory calender perhaps: USe: T-code: OVR3/OY05
Or Change the Factory calender of the Customer: in XD02 in the Sales Areas billing Screen.
Regards,
A S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.