Dear Friends,

We have one typical requirement in our project.

During delivery creation from sales orders all the items get copied from order to delivery.

Suppose there are 50 items in delivery (that is number of line items will be 500).

We want that 30 items should go in one delivery, whereas remaining items in other delivery.

That is all the items in order should go for delivery creation in multiple of 30, that is if order had 100 items (that is 1000 lines) , then 4 deliveries should be created for 30, 30, 30 & 10 items.

Please suggest how this can be achieved.

Regards,

Dhananjay

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Issue Stands Resolved

Former Member
0 Kudos

Hi Dhananjay,

Can you please explain how did you solve this issue. Because i too have a same requirement to resolve.

Thanks and Regards,

Swamy H P

Jelena
Active Contributor
0 Kudos

See "Subsequent Delivery Split" in SPRO, there is documentation available. Also use Search button.