on 12-22-2008 7:39 AM
Hi Experts,
I attached a BOM to an activity. When i save the project and check in MD04, an Order Reservation is created. But i want a planned order to be created. Please suggest what could be the error. What settings have to be changed?
Thanks & Regards,
Kabir
Hi,
That is standard SAP behavior. In order to address your requirement, development will be required. You can consider developing a Z transaction, which will be combination of CN33 and MD02, in short after BOM transfer MRP will run automatically.
Regards