how to release investment program budget

Former Member
0 Kudos

Hi expert:

We distribute original budget in investment program using Tcode Im32, but our customer require to release

original budget , because two position require to approve this budget.

We use Tcode Im52 to distribute budget to project, our customer also approve this operation. but i donot know

whether the system provide standand release function.

how to realize this two functions? thank you

Accepted Solutions (0)

Answers (3)

Answers (3)

nitin_patoliya
Active Contributor
0 Kudos

You are distributing budget from Investment prog. to project.

In IM there is not concept of Budget release. If you want to control your budget at Release ( which is called Active budget control ) you have to does the same in PS.

Your flow would be like that

IM32 :Change origional Prog. budget

IM52 : Budget distribution from Prog to measue i.e. Project/ WBS.

CJ32: Change release Budget. ( so, sys will check budget against this release budget )

For using Release budget funcation you have to activate avalability control in your Budget profile (OPS9 txn ) for the Release & assign that budget profile to budget profile.

Refer this online material

http://help.sap.com/erp2005_ehp_04/helpdata/EN/c4/5dbfa8e7cc11d496eb0000e835339d/frameset.htm

Regards

Nitin

Former Member
0 Kudos

Hi,

You can combine these 2 steps:

1. budget distribution, IM52

2. release budget in PS, CJ32. you need to activate release in your budget profile in PS.

HTH

Former Member
0 Kudos

can release by CJ30.....

just try and get back to me