on 12-20-2008 2:04 PM
Hi expert:
We distribute original budget in investment program using Tcode Im32, but our customer require to release
original budget , because two position require to approve this budget.
We use Tcode Im52 to distribute budget to project, our customer also approve this operation. but i donot know
whether the system provide standand release function.
how to realize this two functions? thank you
You are distributing budget from Investment prog. to project.
In IM there is not concept of Budget release. If you want to control your budget at Release ( which is called Active budget control ) you have to does the same in PS.
Your flow would be like that
IM32 :Change origional Prog. budget
IM52 : Budget distribution from Prog to measue i.e. Project/ WBS.
CJ32: Change release Budget. ( so, sys will check budget against this release budget )
For using Release budget funcation you have to activate avalability control in your Budget profile (OPS9 txn ) for the Release & assign that budget profile to budget profile.
Refer this online material
http://help.sap.com/erp2005_ehp_04/helpdata/EN/c4/5dbfa8e7cc11d496eb0000e835339d/frameset.htm
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can combine these 2 steps:
1. budget distribution, IM52
2. release budget in PS, CJ32. you need to activate release in your budget profile in PS.
HTH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
can release by CJ30.....
just try and get back to me
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.