on 12-19-2008 5:53 AM
Dear All,
Is it possible to book cost on wbs which is not yet released.
If yes , then does it have any effect on AUC.
Regards,
Vishal
No it is not possible to book cost on WBS in CRTD status.
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You have to Release the WBS for booking cost. that is prerequisite.
say for ex. if sys is allowing you to post cost in CRTD status & at the same itme system is allowing you to delete WBs in CRTD status , which is contradictory........ to the basic fundamental.
Please refer this link.
http://help.sap.com/erp2005_ehp_04/helpdata/EN/ee/41f79346ee11d189470000e829fbbd/frameset.htm
Regards
Nitin
Edited by: Nitin Patoliya on Dec 19, 2008 11:37 AM