I have trying to find out solution with trail and error basis but.....
The issue is :
Network activity - Planned duration 100hrs
periodic confirmation taken place .... no problem... actual cost also updated accordinly,
at one point of time, realised that activity is completed with 70hrs effort only.
then I have updated 100% completion.
what is the twist here is:
though I have completed 100% of work with 70% of actual hours, however, system display actual costs equals to 100hrs.
I can not reduce planned hours equal to actual hours. at the same, I would like to see my activitiy completed with 70 hrs and actual cost equal to 70hrs of effort only.
is there any enhancement there so that we can have both display planned 100 hrs and actual as 70 hrs.
and costs also.
Looking forward to hear from the gurus and thanks in advance
Shal award points for appropriate answer.
Regards,
PSR
Hi,
One probable solution would be using User status which will block additional confirmations. At the point when you know that work is completed within planned hours, set this user status so that no more confirmation is possible, at th same time user will come to know that activity is completed.
Hope this helps.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You can put the 70 Hrs manually as the actual data in "activity confirmation" screen ( at the bottom.there is provision to enter actual hours) and also tick the final confirmation as 100%. This will set the status as actvity is fully confirmed and will post 70 Hrs against planned 100Hrs.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.