on 12-18-2008 2:53 PM
Hi,
It's possible to make the standard report (T-Code MCTA) by day or by week.
The selection of period to analyse must be from day to day.
Thanks in advance for your reply
Dear Freind,
The Updatation of The LIS takes Place from the Statistics Keys :
Such As Sales Organization and Customer Material.
Go to T-code: OMO1
there change the infotype Update as required Ashroyonous to Daily.
So the Same Will be Updated on Daily Basis.
Next Go OVRO, OVRP to check the Update.
in the flexible analysis Data Basis you can enter the field for the Data and Create a Infotype and Evaluaton structure.
you will get the REPORT ON dATE BAISIS.
IF NOT SOLVED REVERT BACK
REGARD,
A S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi omar
But say if you have put in days and when you want to see data of last 2 weeks then you can change the From date & To Date for 2 weeks and then you can check the report
Making analysis of all 3 at the same time is not possible as you can select only 1 in OMO1. But if you want to go then you need to go for enhancements and , it is better to integrate with the ABAP'er and give your requirements and ask him that you want all three to make analysis .
Regards
Srinath
User | Count |
---|---|
90 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.