on 12-18-2008 9:48 AM
Dear Friends,
I have a requirement in which I want to Nest 3 Sub Hu's into 1 Main HU.
The problem is that the Sub HU's can be assigned to different Process Orders and not yet in stock.
And when I am trying to Repack these 3 Sub HU's with different process orders , system is not allowing me to do the same and giving message like
" HU XXXXXX is assigned to an object that cannot be processed here".
That means that system doesn't allow nesting of SubHU's assigned to different process order into 1 Main HU.
Has anyone faced this problem ? Can I get some input how can I move ahead with my requirement.
Regards,
Harsh
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
OK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.