Hi Friends,
We are using ASSEMBLY process.
We have a problem in project delivery. Once delivery completes for the required quantity from the CNS0 again system should not show the same quantity for the same project.
But for one WBS system is displaying the required quantity again and again and issuing a new delivery number always.
Can any body please give the possible reasons if any.
Looking forward for your immediate reply.
Thanks in advance.
Reddy
Hi,
you generatng delivery no.. but not doing gods posting... thats why required quantity showing remaining ssame...
unless & untill you post the goods system will allow you to create Delivry docs...
so after creating delivery doct just post goods.....( PG)
Venkatesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.