Hi,
While defining a project in CJ20N the system is automatically defaulting a company code. Can you let me know where to check and change that company code.
thanks and regards
Sri
Hi,
Company code is defaulted in CJ20n from Project profile ( T code OPSA).
Go to SPRO-Structures-Operative Structures-Work Breakdown Structure (WBS)- Create Project profile
Check Organization tab. You will find company code maintained here.
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Srihari,
In OPSA transaction, you can define the company code for your project profile.
Note: Once you create the project with the some project profile and saved it, then if you edit the project profile in OPSA and changed the company code, and same will not reflect on the project those who created already. The updated (changed) project profile will fucntion only for the new project creation.
Hope it is more clearful for you. Appreciate with points if it helpful.
Thanks and Regards
Vetrivelan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.