on 12-17-2008 7:29 AM
Hi,
In product view, I have created a forecast and run product heuristic and no planned orders are getting generated. I checked PPM is available for the product.
Please advise.
Regards
R. Senthil Mareeswaran.
Hi senthil,
Check if the forecast date is beyond PPDS horizon.
Also in product master on PPDS tab, you should maintain 4 in PP Planning procedure.
Bye.
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It can be due to many reasons:
1, Check the Validity dates of PPM
2, Check the Procurement type in Product Master (E or X)
3. Check the PPDS Planning time Fence. Heuristics does not plan within that period.
4. Check the Stock available and the lot size procedure and Qty
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.