on 03-01-2006 10:58 PM
Hi
I have 2 SCs in 2 different tracks
SC1 contains EJBs
SC2 contains FE components
since the FE components need to leverage the EJBs I have set up track connections (of type transport) between the 2 SCs (SC1 = source, SC2 = target)
now i need to develop a new feature, that requires changes both in the EJB and in a FE component
it seems like i cant start working on the FE component, until the EJB changes are in production, as the track connection will only transfer the SP to SC2 after it is deployed to production...
I need to work on both components in the same time, and deploy the 2 SPs together?
is it possible?
please try to avoid gicing a solution that involves changing my SC design...
I have made it sound simplistic here for the sake of the SDN quesion, but in reality I have more than 2 SCs and they are interdependent in a way that I have to have all SCs with EJBs in Track1, and all SCs with front end compoenents in Track2.
Thank you
Zach Engel
Check Point
Hi Zach,
Apart from waiting till your first set of developments are approved and ready for import in the second track, i dont think there is any other way.
Regards
Sidharth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.