on 12-16-2008 11:18 AM
Dear Guru's,
What all the setting that we need do to execute the Project system reports that are available in standard SAP. ex: like CN45N - Orders and please provide the transaction code of all the reports.
Regards,
Bha
Edited by: BHANU SAPPS on Dec 16, 2008 12:19 PM
you need to settings in SPRo--> PS --> Information sys.
Database profile OPTX
Project view for the information system OPUR
Status selection profile BS42
PS info profile : OPSM
Define profiles for the calling overviews : OPSL
Import Hieraachy reports CJEQ
Import costelement report OKSR
Maintain summarization Hierarchy KKRO
If you have changed any setting specif to project than run this txn at last.
Rebuild project infor data base CJEN
also refer this link
http://help.sap.com/erp2005_ehp_04/helpdata/EN/80/94853478616434e10000009b38f83b/frameset.htm
Reporting Tcodes in PS
Line Item reports
CJI3 Actual Costs/Revenues
CJI5 Commitments
CJI4 Planned Costs/Revenues
CJIB Budget
CJIA Actual Payments/Payment Commitments
CJI9 Hierarchical Cost/Revenue Planning
CJIC Display Project Settlement Line Items
CJID Display Project Settlement Line Items
Reports on revenues and earnings.
S_ALR_87013562 Annual Overview
S_ALR_87013563 Structure
S_ALR_87013564 Plan/Actual/Variance
S_ALR_87013566 Actual Contribution Margin
S_ALR_87013567 Quotation/Order/Plan/Actual
S_ALR_87013568 Project Result
S_ALR_87013569 Incoming Orders/Orders on Hand
S_ALR_87013570 Actual/Plan/Absolute Variance/% Variance %
S_ALR_87013571 Actual - Plan- Comparison per Period
S_ALR_87013572 Project Result
Progress Information
CNE5 Progress Analysis: Structure Overview
S_ALR_87015124 Progress Analysis: Project Hierarchy
S_ALR_87015124 Progress Analysis: Detail
CNMT Milestone Trend Analysis
Material Information
S_ALR_87015076 Material Components
MD04 Requirements/Inventory
CO24 Missing Parts
MD09 Pegged Requirements
MD4C Order Report
MB25 Reservations
S_ALR_870156067 Planned Orders
ME3K Outline Agreements
MBBS Valuated Project Stock
ME5J Purchase Requisitions for Project
ME5K Purchase Requisitions for Account Assignment
ME2J Purchasing Documents for Project
ME2K Purchase Orders for Account Assignment
Structure information
CN41Structure Overview
S_ALR_87015065 Individual Overview: Project Definition
S_ALR_87015066 Individual Overview: WBS Elements
S_ALR_87015069 Individual Overview: Networks
S_ALR_87015070 Individual Overview: Activities
S_ALR_87015068 Individual Overview: Orders
S_ALR_87015077 Individual Overview: Sales Documents
S_ALR_87015078 Individual Overview: Sales Document Items
S_ALR_87015072 Individual Overview: Relationships
S_ALR_87015073 Individual Overview: Milestones
CF16 On Materials
CF17 On Document
CF15 On PRT Master
CF18 On Equipment
CN60 On Project/Network
Cost Reports
S_ALR_87013532 Plan/Actual/Variance
S_ALR_87013533 Plan/Actual/Commitment/Remaining Plan/Assigned
S_ALR_87013538 Project Version Comparison: Actual/Plan
S_ALR_87100185 Actual Costs per Month, Current Fiscal Year
S_ALR_87100188 Actual Costs: Aggregated
S_ALR_87100189 Actual/Planned Time Series
S_ALR_87100190 Actual/Plan/Variance per Project and Person Responsible
S_ALR_87013540 Forecast
S_ALR_87013541 Project Interest: Plan/Actual
S_ALR_87013542 Actual/Commitment/Total/Plan in Controlling Area Currency
S_ALR_87013543 Actual/Plan/Absolute Variance/% Variance %
S_ALR_87013544 Actual - Plan- Comparison per Period
S_ALR_87013545 Actual: Period Comparison
S_ALR_87013546 Commitments: Period Comparison
S_ALR_87013547 Plan: Period Comparison
S_ALR_87013548 Statistical Key Figures/Periods
S_ALR_87013549 Actual - Plan- Comparison, with Partner
S_ALR_87013555 Project Result
S_ALR_87013556 Funds Overview
S_ALR_87013558 Plan/Actual/Commitment/Remaining Plan/Assigned
Display Material in Project
CO46 Order Progress Report
S_ALR_87015076 Material Components
Summarized cost reports
S_ALR_87013576 Summarization Overview: Project Hierarchies
S_ALR_87013577 Summarization: Costs/Revenues/Expenditures/Receipts
S_ALR_87013578 Plan/Actual/Variance
S_ALR_87013579 Plan/Actual/Commitment
S_ALR_87013580 Actual/Plan/Variance
S_ALR_87013581 Actual/Plan/Commitment
S_ALR_87013582 Current/Cumulative/Total
S_ALR_87013583 Budget/Actual/Variance
S_ALR_87013584 Budget/Actual/Commitment
S_ALR_87013585 Plan/Actual/Variance
S_ALR_87013587 Actual Contribution Margin
S_ALR_87013588 Order Result
S_ALR_87013589 Actual/Plan/Variance
S_ALR_87013590 Current/Cumulative/Total
S_ALR_87013591 Payment Summarization: Overview
Payment Reports
S_ALR_87100191
Payments: Receipts/Expenditures for a Fiscal Year
KSB5 Document Display: Actual Costs/Revenues
CJ3B Document Display: Budget
CJIG Document Display: Payments
S_ALR_87013573 Payments: Receipts/Expenditures for all Projects
S_ALR_87013575 Payments: Receipts
S_ALR_87013574 Payments: Expenditures
-
Regards
Nitin
Edited by: Nitin Patoliya on Dec 16, 2008 7:03 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
U can access all the PS related reports from Easy access menu...Logistics->Project System-> Information System
Following are the some of the strcuture related reports........
CN40 Project Overview
CN41 Structure Overview
CN42 Overview: Project Definitions
CN42N Overview: Project Definitions
CN43 Overview: WBS Elements
CN43N Overview: WBS Elements
CN44 Overview: Planned Orders
CN44N Overview: Planned Orders
CN45 Overview: Orders
CN45N Overview: Orders
CN46 Overview: Networks
CN46N Overview: Networks
CN47 Overview: Activities/Elements
CN47N Overview: Activities/Elements
CN48 Overview: Confirmations
CN48N Overview: Confirmations
CN49 Overview: Relationships
CN49N Overview: Relationships
CN50 Overview: Capacity Requirements
CN50N Overview: Capacity Requirements
CN51 Overview: PRTs
CN51N Overview: PRTs
CN52 Overview: Components
CN52N Overview: Components
CN53 Overview: Milestones
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
U can use search by using this option also.
search_sap_menu...........................TCode
u can easily search.
SAP1...TCode.......search for PS Module.
SAP2......Tcode........for INFO CATALOG.
I hope so your req will fulfill.
Regards
Chandra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.