on 12-16-2008 4:52 AM
Dear Team,
Regarding ME2o,
My analysis is when we need to execute the ME2o, prior to that we need to generate the PO, in the PO, material should belongs to BOM.
In the BOM, sub components ( Child items) are are belongs to different PO for the same vendor then, delivery is splitting. Why delivery is splitting and is there any process to have single delivery even sub componenets are belongs to different PO of same vendor.
Thanks & Regards
Bhaskara
Hi,
That's right, the latent splitting rule of delivery note creation is the PO number, you had better put all components of subcontracting part into the same PO.