on 12-15-2008 1:41 PM
Hi there,
Does anyone know where TX KP26 Planned Activity value is used? In what programs & the reason for the use? etc?
Thanks
Mantas
Let me clarify -
Once you are in change mode for the transaction you are presented with the periods that you've selected.
There you can enter the following:
- Planned Activity (activity quantity) [data element is LSTXX]
- Capacity
- Fixed Activity Price
- Variable Price
- Price Unit
- Equivalence Numbers
I know that the price is the price that will appear on planned / actual postings on the work order, however what I am interested in is the first of those fields - Planned Activity. Any info on that field would be much appreciated.
Thanks
Mantas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Mantas,
1. In KS01 cost center is created
2. In KL01 activity type is created
3. in KP26, activity type is assigned to cost center and activity price is maintained for cost center and activity type combination. Ativity price is nothing but cost per unit of time
4. This cost cnter and activity types are assigned in work center and resource
5. Using work center routing/master recipe are created. and time is maintained for each operation
6. when u create a production/process order, routing/recipe gets copied along with all details.
7. when u confirm the order with time taken, activity price multiplies with time for base qty and activity cost gets calculted and flows to the order.
8. when order settlement is done, header material manufaturing price gets caculated
i hope u r clear
sree
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.