on 12-15-2008 10:51 AM
Dear GURU's,
Can any one please suggest me how to do budgeting at activity level and WBS element level in project systems, friends please I required set by step process.
I need how to do this configuration to map this scenario.
Regards,
Bhanu
Hi
U can assign budget to wbs only not activity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I don't think that budgeting can be possbile at activity level. please refer this link for the budgeting at WBs level.
http://help.sap.com/erp2005_ehp_04/helpdata/EN/d5/74a9371c726343e10000009b38f842/frameset.htm
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bhanu,
Use this link :
http://help.sap.com/saphelp_45b/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm
after page opens , click on BUDGET MANAGEMENT , There you will find each and every step you want .
Thanks ,
Dhruv Kumar Malhotra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.