consideration of network activity factory calender

Former Member
0 Kudos

Hi,

I am facing problem regarding considering of factory calendar.

scenario: we are assigning the personnel nos in person assignment tab in internal activity. confirmation of activities will be done through CATS. at the time of confirmation it is considering the calender given in work scheduling in HR master data rather considering the factory calendar of network activity.

i require how to select the factory calendar of network activity rather selecting the calendar from work scheduling of HR data.

With Regards

Prasanth.N

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Prashant,

This is solution for PS without HR integration..............Please do the following steps:

1. Create a person responsible using OPS6

2. Assign a desired factory calender in the particular activity at internal tab of the activity.

3. Then Plan your work and save and release.

4. Then do the confirmation in CATS

Hope it will be clear now. Appreciate if it is useful

Thanks and Regards

Vetrivelan