on 12-13-2008 11:28 PM
We have an issue.The scenario is : There are Sales Order already created for a material sat mat1 with availability check code "ZF" in MRP3 tab of material master.The MAD has already been calculated with existing settings.
What is required that change the availability check code in MRP3 tab of material master to "ZB" and re-check the availability of the already created sales orders.
But what we understand since Sales Order already created for Availability check code "ZF",new changed "ZB" will not impact the ATP check.
Is there any way this can be achieved.
Manish
Hi,
Just delete the line item from the sales order and re-enter the same line item.
By this way, the line item will take the new availability check code.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.