Not able to create delv from cns0

Former Member
0 Kudos

Dear All ,

User has seen all material properly in CJ20N, now he is creating an Outbound Delv from Project ( CNS0 ) But here problem os that about 30 material code are not comingin CNSO pl help us truck is waiting to move.

Thx & Rgds,

sap2008

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

thanx to all of u for ur efforts.

sap2008

Former Member
0 Kudos

Dear,

We can use CNS0 only when we use stock. after GRN we move the material to stock. After that we do the CNS0 and then we create chalan(VL02n). now we get the document number and on the base of that document number we do the final billing to the customer.

Pls check the whole procedure...

regards

Former Member
0 Kudos

Hi

reason i can guess is

1. check u r using project stock

2. in material master mrp 3 view , individual and collective requirment indicator should be blank or 1.

Former Member
0 Kudos

Can ne body help me ?