service item pgi

Former Member
0 Kudos

Hi

For SAP testing purpose, I simulated order with one service line item and two finished goods , doing the same for delivery and done post goods, but system objects post goods for service item.is there any solution to do post goods or no possibility to dispatch materials without doing post goods?

points will be awarded

Kanna Palle

Edited by: kanna palle on Dec 12, 2008 9:16 AM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

It is possible to post goods issue for service, but it will be called confirmation of service instead of PGI. You need to make sure you assign a schedule line category that is relevant for delivery but not inventory management, such as CX.