Dear Gurus,

I am getting difference of 'Acutal Cost' between S_ALR_87013531 and KKA2

Actually in KKA2 Result analysis for project I am appearing Actual cost under actual data which showing higher than S_ALR_87013531

In S_ALR_87013531 I am appearing actual cost for Overall values

Regards

Honyal

Accepted Solutions (0)

Answers (2)

Answers (2)

hanamanth_honyal
Participant
0 Kudos

Help ful answer

Former Member
0 Kudos

Hi

check following

1. Report is based on the value categories. Whethere you are missing any of the cost element to map for value catergories maintain in OPI2.

2. Is there any cost posted through secondary cost element. Compare it with CJI3

3. Is there any statistical cost posting (i,e. value type 11) it can be seen in CJI3.